Projects

Dierbergs Lakeview Pointe

EVre DC fast chargers at Dierbergs Lakeview Pointe at dusk with the store in the background
Client
Dierbergs Markets
Location
Osage Beach, MO
Year
2025
Value
Equipment modernization

Equipment: 2× 75kW Tritium DC fast chargers (Noodoe network) · NACS + CCS1 connectors · Plug & Charge support

EVre services used: Engineering & Design · Turnkey Project Delivery

At the Lake of the Ozarks’ grocery-anchored Lakeview Pointe center, EVre replaced existing, outdated charging units with new equipment built for this decade’s EV driver — NACS connectors for Teslas without adapters, Plug & Charge convenience, and customer support that actually answers.

Scope highlights

  • Two 75kW Tritium DC fast chargers on the Noodoe network, each with NACS and CCS1
  • Modern payment: card, app, and Plug & Charge
  • 24/7 EVre monitoring with local dispatch — not a national call-center queue

Why it matters for your project

The first generation of charging hardware is aging out at sites all over the Midwest. This is the local solution: a Missouri owner-operator who picks equipment for the site, answers the phone, and treats a grocery anchor’s parking lot like the customer amenity it is. Better than the big guys — because we care, and because we’re here.

“This is perfect. As usual, you guys are a class act — thank you so much for your help.” Dierbergs Markets

Plan a Project Like This